Zeus Mitchell Campus
Enterprise-Scale AI Training Data Center | Texas
Project Overview
Zeus Mitchell Campus is a hyperscale data center complex specifically designed for AI training workloads, featuring enterprise-grade infrastructure, and on-site sustainable power and energy storage solutions.
Campus Highlights
Total Campus Size: 6,000 acres under lease (300+ acres designated for Data Center Complex). Additional 1,900 acres available for expansion.
Total Capacity: 2.1GW Data Center Complex
Configuration: 14 powered shells @ 150MW each
Shell Footprint: 20 acres per shell
First Phase Online: 100+MW by Q2 2027
Total Energy Capacity: 800MWac (Solar), 1,000MW (BESS). Adjacent 1,500MW CCGT for optional expansion (Permitted, Pre-Construction)
Power Infrastructure
Grid Connection & Utility
• Utility Provider: Oncor (Transmission Service Provider & Load Serving Entity)
• Grid: ERCOT (Electric Reliability Council of Texas)
• Transmission: Primary power provided via 345kV Oncor T-line to support 2,100MW DC point of interconnection
• Redundancy: Three breaker ring bus configuration at 345kV
• Grid Fuel Mix: 48% natural gas, 16% solar, 16% wind, 12% coal, 7.5% nuclear
On-Site Power Generation
• Solar Generation: 800MWac utility scale solar project
• Battery Storage: 1,000MW battery energy storage system (BESS)
• Future Expansion: Additional 1,500MW CCGT natural gas plant capability
• Power Integration: Direct behind-the-meter interconnection of solar and BESS to data center
Site & Infrastructure
Location Advantages
• Transportation: Major Texas interstate highway adjacent to site
• Expansion Ready: 6,000+ acres under site control – an additional 1,000 acres available for future expansion if needed
• Environmental: Environmental Critical Issue Analysis (ECIA) complete (July 2023) and Phase I ESA studies complete (Dec 2024) - No environmental areas of concern or protected wetlands identified (Feb 2025)
Land Holdings
• Multiple contiguous parcels totaling 6,000+ acres under lease
• LOIs to purchase 500-600 acres for DC specific use in negotiations on land already under lease control by Zeus
• Largest parcels: 640 acres (multiple), 620 acres, 480 acres, 460 acres
• Strategic parcel positioning for optimal campus development
Connectivity
• Primary Provider: AT&T
• Network Access: Multiple Central Offices within 80km
• Metro Connectivity: Direct links to DASH (Dallas, Austin, San Antonio, Houston)
Development Status & Timeline
Current Phase
• Site control secured with 19 parcels under lease
• Preliminary geotechnical analysis completed
• ECIA, Phase I ESA, and wetlands delineation study finalized (Aug 2024/Feb 2025)
• Utility interconnection studies for load and generation underway with ERCOT/Oncor
• Established strategic partnerships with solar and BESS OEM suppliers and BoP EPC
Next Milestones
• 30-60% design phase for precise micro-siting
• ALTA survey work for final acreage confirmation
• Geotechnical studies for foundation design (completed on adjacent site. No issues expected)
• Transportation impact study with EPC contractor
• Reservation Payments to secure manufacturing slots for long lead-time items (MPTs, etc)
• TAA 312 agreement with Mitchell County
Delivery Timeline
• Q2 2027: First 100+MW shell online
• Phased Delivery: Consecutive construction of additional shells based on tenant requirements
Sustainability & ESG
Renewable Energy Integration
• On-site Solar: 800MW capacity directly serving data center
• Battery Storage: 1,000MW BESS for grid stability and renewable integration
• Grid Mix: 32% renewable sources (16% solar + 16% wind) from ERCOT
• Future Flexibility: Natural gas backup capability for reliability
Environmental Compliance
• No significant wetlands impact
• Stormwater management and prevention planning included
• Rural location minimizes urban infrastructure strain
Permitting Advantages
• Rural Location: No municipal permits, zoning restrictions, or height limitations required
• Streamlined Process: No county or city approvals needed for construction
• Regulatory Relationships: Direct communication established with TCEQ Deputy Director
• Utility Support: Executive buy-in from Oncor for substation permitting
• Experience: Extensive knowledge of local permitting through previous natural gas project development in Mitchell county
Labor & Workforce Availability
Construction Workforce
• Regional Availability: No known constraints for construction labor in the region
• Cost Structure: Accommodates rural conditions with competitive regional rates
• Labor Relations: Right to Work Non-unionized workforce with no history of labor disputes
• Contractor Relationships: Existing relationships with local contractors established
• Commissioning: Qualified commissioning workforce available
• General Contractors: Final negotiations in progress with experienced EPC partners
Specialized Technical Workforce
Electrical Specialists
• Regional Supply: Ample qualified electricians with proximity to major Texas markets
• Scalability: Workforce can scale according to project timeline with staggered implementation
• High-Voltage Expertise: Local high-voltage specialists available
• Data Center Experience: Access to contractors with proven data center experience
• Certifications: Teams working on NEC compliance and critical certifications
• Key Partners: EPE, Mortenson & Worldwide Mission Critical contributing expertise
Mechanical & Plumbing Resources
• HVAC Systems: Experienced mechanics available for facility piping and cooling systems
• Advanced Cooling: Architect experience with direct-to-chip liquid cooling arrays
• Regional Partners: Multiple OEM partners in Dallas/Fort Worth area for installation support
• Timeline Impact: Mechanical workforce not expected to limit overall project timeline
• Vendor Network: Established relationships with regional plumbing and mechanical contractors
Connectivity & IT Infrastructure
• Fiber Infrastructure: Establishing strategic partnership with AT&T
• Redundancy: Minimum of three ingress points for redundant fiber connectivity
• Installation: Connectivity labor availability will not limit build timeline
• Deployment Speed: Service capabilities designed for rapid deployment when needed
Resources & Supply Chain
Material Availability & Logistics
• Heavy Machinery: Multiple regional suppliers with no sourcing concerns
• Commodities: No lead time differences for concrete, steel, and standard materials
• Year-Round Access: All-weather site access with no seasonal build restrictions
• Working Hours: No local constraints on construction hours or times
• Environmental Approvals: No anticipated restrictions on build hours
Equipment & Storage Solutions
On-Site Capabilities
• Warehousing: Suitable regional warehousing available; on-site staging areas prepared
• Equipment Storage: Secure perimeter and storage for materials and equipment
• Weather Protection: Weatherization protection for early-arriving specialized equipment
• Material Security: Total control measures for all on-site assets
Critical Equipment Timeline
• Major Power Transformers (MPTs): 16-18 month lead times
• Circuit Breakers: 16-18 month lead times
• Solar & BESS: Just-in-time delivery and installation (Texas standard practice)
• Delivery Coordination: Single delivery scheduling for proper ingress/egress monitoring
Supply Chain Advantages
• Regional Sourcing: Access to Dallas/Fort Worth industrial corridor
• Multiple Suppliers: Diversified supplier base reduces risk
• EPC Confirmation: Lead times and availability confirmed by multiple EPC contractors
• No Bottlenecks: Working with EPC teams to ensure no workforce bottlenecks
Key Competitive Advantages
Scale & Flexibility
• Hyperscale capacity with modular deployment options
• 2-story or 3-story shell configurations available
• Massive land availability for tenant-specific requirements
Power Reliability
• Rural power distribution demonstrably more reliable than urban
• Multiple power sources: grid, solar, battery, future gas
• No extraordinary vulnerabilities predicted for power access
Infrastructure Readiness
• Suitable foundation conditions across campus footprint
• Multiple suitable access roads for construction and operations
• Ample space for parking and construction staging
Strategic Location
• Texas business-friendly regulatory environment
• ERCOT grid participation with competitive power markets
• Proximity to major Texas metros via interstate access
Tax Abatement Agreements (TAA) and Value Limitation Agreements (VLA)
• Solar/BESS have TAAs in place with county, DC will negotiate and enter into a TAA in the next 4-6 months (Texas Tax Code Section 312)
• Solar/BESS have in place executed VLA – VLA program no longer available (Texas Tax Code Section 313)
• Additional 1,500MW CCGT site sits on directly adjacent land that is already owned outright, and has legacy SGIA, Air Permit, Geo-tech, 312 tax abatements, etc.
Technical Specifications
Power Configuration
• 345kV grid connection with Oncor ownership of high-side substation
• Low-side substation wholly owned by Zeus/tenant
• Three breaker ring bus configuration for maximum reliability
Site Preparation
• Buildability assessment completed
• No significant geotechnical concerns identified
• Flexible design accommodation for tenant requirements
Operational Support
• DCIM management options available based on final design
• Local warehousing capabilities for equipment staging
• EPC contractor coordination for construction logistics
Contact Information
For detailed specifications, site visits, or lease discussions, please contact the Zeus development team. Trey Berndt; trey@zeusred.com
This fact sheet is based on the official Zeus Mitchell Campus RFI documentation dated May 1, 2025.
Data Center
Fiber