Zeus Armstrong Campus
Enterprise-Scale AI Training Data Center | Texas
Project Overview
Zeus Armstrong Campus is a hyperscale data center complex specifically designed for AI training workloads, featuring enterprise-grade infrastructure, and on-site sustainable power and energy storage solutions.
Campus Highlights
Total Campus Size: 5,100 acres under lease (300+ acres designated for Data Center Complex). Additional 800 acres available for expansion.
Total Compute Capacity: 1.05GW Data Center Complex
Configuration: 7 powered shells @ 150MW each
Shell Footprint: 20 acres per shell
First Phase Online: 100+MW by Q2 2027
Total Energy Capacity: 500MWac (Solar), 1,000MW (BESS)
Power Infrastructure
Grid Connection & Utility
• Transmission Service Provider: Oncor
• Load Serving Entity: Greenbelt Electric Cooperative
• Grid: ERCOT (Electric Reliability Council of Texas)
• Transmission: 1,050MW transmission connection via 345kV lines from Alibates substation
• Grid Fuel Mix: 48% natural gas, 16% solar, 16% wind, 12% coal, 7.5% nuclear
On-Site Power Generation
• Solar Generation: 500MWac solar farm
• Battery Storage: 1,000MW battery energy storage system (BESS)
• Power Integration: Direct behind-the-meter interconnection of solar and BESS to data center
Site & Infrastructure
Location Advantages
• Access: Multiple suitable existing roads for ingress and egress, with CR 207 running adjacent to key parcels
• Transportation: Major Texas interstate highway within close proximity
• Expansion Ready: 5,000+ acres available for future development (additional 800+ available for future expansion)
• Environmental: Environmental Critical Issue Analysis (ECIA) complete (July 2023) and Phase I ESA studies complete (Dec 2024) - No environmental areas of concern or protected wetlands identified (Feb 2025)
Land Holdings
• Multiple contiguous parcels totaling 5,000+ acres under lease
• LOIs to purchase 500-600 acres for DC specific use in negotiations on land already under lease control by Zeus
• Contiguous Block 1: 1,875 acres
• Contiguous Block 2: 3,199 acres
• Strategic parcel positioning for optimal campus development
Connectivity
• Primary Providers: AT&T (primary) and Windstream
• Fiber Access: Three viable fiber laterals to Central Offices within 26-65km
• Network Reach: Multiple Local COs within 80km of campus
• Metro Connectivity: Direct links to DASH (Dallas, Austin, San Antonio, Houston)
Development Status & Timeline
Current Phase
• Site Control secured through multiple contiguous parcels under lease
• Preliminary site analysis and buildability assessment completed along with preliminary geotechnical analysis
• ECIA, Phase I ESA, and wetlands delineation study finalized (Dec 2024/Feb 2025)
• Utility interconnection studies underway with ERCOT/Oncor
• Load studies commenced by Oncor for project load ramping
• 312 tax abatement executed for solar and BESS assets; data center 312 tax abatement planned for summer 2025 with tenant input
Next Milestones
• 30-60% design phase for precise micro-siting
• ALTA survey work for final acreage confirmation
• Geotechnical studies for foundation design
• Transportation impact study with EPC contractor
• PO for long lead items (Main Power Transformers, solar modules, etc.)
• TAA 312 agreement with Armstrong County
Delivery Timeline
• Q2 2027: First 100+MW shell online
• Phased Delivery: Consecutive construction of additional shells based on tenant requirements
Sustainability & ESG
Renewable Energy Integration
• On-site Solar: 500MW capacity directly serving data center
• Battery Storage: 1,000MW BESS for grid stability and renewable integration
• Grid Mix: 32% renewable sources (16% solar + 16% wind) from ERCOT
• Clean Energy Focus: On-site solar and battery storage providing sustainable power solutions
Environmental Compliance
• EIA (July 2023) and Phase I ESA (December 2024) completed with no liabilities identified
• Wetlands delineation study (February 2025): 109 emergent wetlands identified but none prohibitive to development
• Endangered species assessment: Only Tricolored Bat with "moderate" occurrence likelihood - mitigation via avoidance and setbacks
• No air quality permits required for campus operations
• Stormwater management and prevention planning included
• Rural location minimizes urban infrastructure strain
• 312 tax abatements secured for renewable energy assets with data center abatements planned for 2025
Permitting Advantages
• Rural Location: No municipal permits, zoning restrictions, or height limitations required
• Streamlined Process: No county or city approvals needed for construction
• Regulatory Relationships: Direct communication established with TCEQ Deputy Director
• Utility Support: Executive buy-in from Oncor for substation permitting
• Experience: Extensive knowledge of local permitting through previous wind project development in county
Labor & Workforce Availability
Construction Workforce
• Regional Availability: No known constraints for construction labor in the region
• Cost Structure: Accommodates rural conditions with competitive regional rates
• Labor Relations: Right to Work state and non-unionized workforce with no history of labor disputes
• Contractor Relationships: Existing relationships with local contractors established
• Commissioning: Qualified commissioning workforce available
• General Contractors: Final negotiations in progress with experienced national EPC partners
Specialized Technical Workforce
Electrical Specialists
• Regional Supply: Ample qualified electricians with proximity to major Texas markets
• Scalability: Workforce can scale according to project timeline with staggered implementation
• High-Voltage Expertise: Local high-voltage specialists available
• Data Center Experience: Access to contractors with proven data center experience
• Certifications: Teams working on NEC compliance and critical certifications
• Key Partners: EPE, Mortenson & Worldwide Mission Critical contributing expertise
Mechanical & Plumbing Resources
• HVAC Systems: Experienced mechanics available for facility piping and cooling systems
• Advanced Cooling: Architect experience with direct-to-chip liquid cooling arrays
• Regional Partners: Multiple OEM partners in Dallas/Fort Worth area for installation support
• Timeline Impact: Mechanical workforce not expected to limit overall project timeline
• Vendor Network: Established relationships with regional plumbing and mechanical contractors
Connectivity & IT Infrastructure
• Fiber Installation: Connectivity labor availability will not limit build timeline
• Deployment Speed: Service capabilities designed for rapid deployment when needed
• Redundancy: Multiple ingress points for redundant fiber connectivity through diverse fiber laterals
Resources & Supply Chain
Material Availability & Logistics
• Heavy Machinery: Multiple regional suppliers with no sourcing concerns
• Commodities: No lead time differences for concrete, steel, and standard materials
• Year-Round Access: All-weather site access with no seasonal build restrictions
• Working Hours: No local constraints on construction hours or times
• Large Load Delivery: Site designed to accommodate oversized loads for data center construction
Equipment & Storage Solutions
On-Site Capabilities
• Warehousing: Suitable regional warehousing available; on-site staging areas prepared
• Equipment Storage: Secure perimeter and storage for materials and equipment
• Weather Protection: Weatherization protection for early-arriving specialized equipment
• Material Security: Total control measures for all on-site assets
Critical Equipment Timeline
• Major Power Transformers (MPTs): 16-18 month lead times
• Circuit Breakers: 16-18 month lead times
• Solar & BESS: Just-in-time delivery and installation (Texas standard practice)
• Delivery Coordination: Site designed for proper ingress/egress of construction materials
Supply Chain Advantages
• Regional Sourcing: Access to Dallas/Fort Worth industrial corridor
• Multiple Suppliers: Diversified supplier base reduces risk
• EPC Confirmation: Lead times and availability confirmed by multiple EPC contractors
• No Bottlenecks: Working with EPC teams to ensure no workforce bottlenecks
Key Competitive Advantages
Scale & Flexibility
• Hyperscale capacity with modular deployment options
• 2-story or 3-story shell configurations available
• Massive land availability for tenant-specific requirements
Power Reliability
• Rural power distribution demonstrably more reliable than urban
• Multiple power sources: grid, solar, battery
• Dual utility relationship with Oncor (TSP) and Greenbelt Electric Cooperative (LSE)
Infrastructure Readiness
• Suitable foundation conditions across campus footprint
• Multiple suitable access roads for construction and operations
• Strategic parcel layout with two major contiguous blocks
Strategic Location
• Texas business-friendly regulatory environment
• ERCOT grid participation with deregulated competitive power markets
• Proximity to major Texas metros via interstate access
• Multiple fiber connectivity options with diverse routing
Tax Abatement Agreements (TAA) and Value Limitation Agreements (VLA)
• Solar/BESS have TAAs in place with county, DC will negotiate and enter into a TAA in the next 4-6 months (Texas Tax Code Section 312)
• Solar/BESS have in place of executed VLA – VLA program no longer available (Texas Tax Code Section 313)
Technical Specifications
Power Configuration
• 1,050MW transmission connection via an Oncor mid-point tap of the 345kV double-circuit T-line (23914 Tule Canyon – 23900 Alibates).
• Oncor transmission service with Greenbelt Electric Cooperative load serving
• Low-side substation wholly owned by Zeus/tenant
• High Side Three breaker ring bus configuration for maximum reliability
Site Preparation
• Buildability assessment completed
• No significant site constraints identified
• Flexible design accommodation for tenant requirements
Operational Support
• DCIM management options available based on final design
• Local warehousing capabilities for equipment staging
• EPC contractor coordination for construction logistics
Contact Information
For detailed specifications, site visits, or lease discussions, please contact the Zeus development team. Trey Berndt - trey@zeusred.com
This fact sheet is based on the official Zeus Armstrong Campus RFP documentation dated April 25, 2025.
Data Center
Fiber